Uh hi Son. Uh let's wait for some time
Okay. Uh let's start the session. Uh
>> okay sir. Okay.
>> Yeah. Uh just share your screen and show
me what you have done in the exercise.
Then you will start.
sir is my window is visible. >> Yes.
>> So what you have done
>> sir? Uh
I created project inside the project I
uh as in calendars. >> Okay.
>> Okay.
>> WBS I created
>> and under WBS and added activities
>> up to that level only. I still I didn't
link anything.
So this is my project.
>> Links we have not yet seen right. Okay. >> Okay.
>> Okay.
So this is my project.
>> Any issues? any issues you faced or
everything fine?
>> Yeah, everything is fine up to here. No,
no issue for me. Then these are all my
milestones and under milestones,
these are the activities. M
M
>> and then
and then engineering. >> Okay.
>> Okay.
>> And then procurement. My scope is only
uh civil structural piping and equipment installation.
And under under procurement
construction construction activities.
>> Okay. And there are three WBS. Okay.
Civil structure.
>> The duration is 4 days or 400 days.
>> 4 days. 4 days.
Default default duration I it is taken 4
days only. I didn't change it.
>> Okay. Fine. Fine. Okay.
So in this civil foundation including
equipment and structural foundation both
are considered here and then
>> mechanical works
>> and piping works in piping fabrication
>> Okay. So lot of activities added very
good. Okay.
>> Okay. Uh Sish, how about you?
>> One second, sir. I may sir. >> Yes.
>> Yes.
I audible sir?
>> Yes. Yes. Audible.
>> Uh uh sir I am busy now. Uh I created
this uh first island like and uh I
created this uh WPS. >> Mhm.
>> Mhm.
EPS. Okay.
>> Yeah. Inside this I created this uh Okay.
>> Okay. >> Yes.
>> Yes. under
and procurement also this
I'm working in on it after completion
after two days I will complete so I have
a lot of work sir
>> okay uh so you have done till WPS Yes.
>> Yeah. Yeah.
>> Okay. Fine.
>> But uh and I have the doubt.
Uh actually uh this one is for projects. Okay.
Okay.
It is looking like a WBS maybe strategic
fuel reserve is one project under that
you have WBS of DAL tanks it is like
that or or everything is different
different projects yeah different
Preconstruction. Mhm.
Okay, sir.
Island gas. oil and gas portfolio.
Okay. Okay.
different. Okay.
Okay. Any other doubt?
Okay. Okay. Okay. Uh
Uh
Rohit have you done your exercises or
>> Yes sir. No problem. No problem.
>> No problem. So you have done your exercises.
>> First class I mean the second class
Tamil member
Okay. Okay. Okay. Sure. Okay.
Okay. So WBS creation and alignment it
is completed. So I'm just highlighting
activity creation. Activity creation.
So let's see today also. Okay.
Okay.
>> Okay. Right.
>> Yes sir.
>> So what we have done is we have created
some activities and we gave some durations.
durations.
Okay. Um
there is a rule in construction when you
are giving this uh activity duration for
activities. Okay. The rule is uh
basically uh
if if we are out of construction the
rule is uh 8 by 80. It is called 8 by 80
so this is the rule. Okay. An activity
should have at least 8 hours and it
should not exceed 80 hours.
Okay, which means uh activity duration
should be at least 1 day or 10 uh
maximum 10 days. Okay, this is general rule.
rule.
Okay, but uh what we have in in
construction it is it is not possible to
have 10 days for activities. What will
happen if I'm giving just 10 days for
this site store establishment? I have to
break down into three activities. So 10
days, 10 days, 8 days like that, right?
Maybe site store uh I I have to break
down this activity basically. Site
office establishment 21 days I have to
break down into two 10 10 days. Uh
office installment then uh office
service work like that I have to break
down. Okay. But in construction we have
that exceptions. We can have 28 days
maximum in any uh activity. Not just 10
days. We can have up to 28 days we can
have we should not have more than 28
days. Okay, that will not give proper
critical path and it is not the right
thing to do. Imagine if if I have an
activity I'm giving 90 days duration.
Okay, uh my total project duration is 1
year 360 days. I have four activity 90
days. So what will happen? That activity
will not get updated till 90th day. 90
days it will be sleeping that activity
right? we we cannot close that activity
for 90 days. So that is not a proper
project monitoring. So we have to break
down that three activities so that
monthly once we can close one activity.
Okay. So that is why uh we are having
this rules. We should not have more than
28 days. If it is having more than 28
days, we have to break down that
activity. Example uh if you are having u
if you're having like uh what we are
seeing here is a tunnel works right to
to do 1 kilometers of tunneling it will
take 120 days but I cannot give 120 days
for tunnel one tunnel 2 120 days tunnel
3 120 days I cannot give like that so
tunnel one I have to break down earth
work 30 days after that concreting works
30 days then inside tunnel works 30 days
like that I have to break So uh 30 means
28 days. Okay. Uh that is what uh in a
month we will have working days more or
less 24 to 28 not more than that. Okay.
That is why the 28 days rules is there.
Okay. Just keep that in mind. If you
have a bigger activity just to break
down into two or three uh that will uh
that will allow us to do the better
monitoring in a project. Okay. Now, so
how to give uh this name uh activity
names and this duration we have seen.
Now let's switch to this uh
activity ID. Okay, this activity ID is
important for identifying the activity.
Okay. Uh this one
basically if someone just seeing the
activity you see if in engineering we
will have a drawing uh drawing
submissions right drawing submission and
approach let's say one uh drawing name
okay uh civil coordination layout okay
so we will have activity civil
coordination layout and drawing
submission for submission for approval
also we will have the same activity
civil coordination layout here we will
submit here we will approve
But I'm not seeing this heading. I'm
just seeing the activity civil
coordination layout. How will I identify
it is submission activity or approval
activity? I may get confused. Okay. Uh
it is uh when you are having activities
3,000 4,000 activities in a schedule.
Lot of time you will have this uh
confusion. Uh for example, I I will give
better example. We have 20 floor
building. Okay. In floor one uh concrete
pouring we have an activity floor two
also we have a concrete pouring floor
three till floor 30 we are having that
concrete pouring activity or slab
activity most of the activities are
repeated activities okay we are not
having unique activities uh in buildings
if you are having 20 floors when when
it's to typical floors even quantity
also will be same okay uh there we have
to identify which floor this activity
belongs to okay so we have to identify
that identification we can do based on
activity ID so here so this all
activities are preconstruction
activities it is under preconstruction
okay now I'm seeing the heading it is
okay but when I
copy pasted this to excel and I'm
sharing to someone and they are doing
the filter okay at that time they will
get confused even we will get confused
okay that is why this ID is important So
uh the ID should be unique and it should
be identifiable also. Okay. So here I'm
just giving an example the way uh when I
am working as a planner. This is the way
I used to follow. This is what my boss's
artial time also taught me. Okay. I will
just show this. Okay. You just select
this activity. Select all activity.
Okay. To select all activities. Right
click. Go to renumber activity ids.
Okay. There you will have a three
options. The first option if you give
all activity will be just 10 10 uh
numbers different that is already here.
See 8,000 8,10 8, 20, and 30. This is
what by default this method is selected.
But I don't want that one. I want to
give numbering auto number. So I have I
can I have to give some prefix and some
suffix. Prefix in uh prefix in letters,
suffix in numericals. Okay. The last two
value is for unique identity. So I will
give you examp when I'm giving example
you will have a better understanding of
this. Okay. See in in my organization if
I'm having number of project first I
have to identify which project this
activity belongs to. Okay. See your
company is having four or five projects.
In main office one guy sitting combining
all the projects and he doing some
reporting works. Okay. On that time he
need to identify which project it
belongs to. So first we have to uh
isolate based on project. Okay my
project name here what I have given
north site utility tunnel set for
education city. Okay. So north site.
So I I'm starting my activity ID is
north site. Then in north site uh
utility tunnels this is belongs to
preconstruction. So I'm giving
preconstruction one identity after that
1,000 number then incremental value
1,000. If I'm clicking okay now you see
a a person seeing this if you have this
unique uh coding method in all of the
project it will be very useful. See
north site preconstruction. So if I'm
seeing receive input drawings okay uh
which project it belongs to okay north
side utility after seeing this I can and
where it is preconstruction
it's a pre-construction activity like
that I can identify right so that is how
you have to give uh this uh activity
numbering okay uh this is very simple
one actually for pre-construction when
I'm doing for engineering um we will
have better understanding let's create
some activities for
Let us create some activities for uh
drawing submission and drawing approvals
then we will move further. Okay, I'll
create here. So we have zone one and
Zone one
mechanical layout.
electrical layout
services
layout. Okay, I have done I have created
four four drawings for zone one. Okay.
So now I'm copying it and I'm pasting it in
in
So now what happen? See I have zone one
civil layout. Here also zone one civil
layout. But just seeing this activity I
don't know whether it is a submission
activity or approval activity. If I'm
seeing in prime aa with WBS I can
understand it is under submission. So
this is submission. This is under
approval. So this is approval. But if
I'm just seeing this in Excel sheet, I
am not able to identify which uh uh
where it belongs to it's a submission or
approval. I don't know that right. So
that is why we need this unique
numbering. Let's give unique numbering here.
here.
Uh before that
let me make
zone two also I do have a zone two right
imagine if we don't give this zone one
zone 2 it all will be messed up civil
layout civil layout you I don't know
which zone also right
so in here we have this zone two so that
we can identify but uh it's a submission
or approval that we will decide based on
this one
so right click renumber activity ids so
north side that is okay and it is not a
preconstruction it is a
engineering activity in engineering it
is a drawing submission
Okay. Now see north side north side
project engineering activity drawing
submission right and here let's copy this
Now here
here
give the re numbering
instead of drawing submission I'm just
changing into drawing approval. So north
side project engineering drawing approvals.
approvals.
So now I will have a better
understanding. Right? So this is how you
have to give some unique identification
but it is up to you even you can follow
the same uh 8,000
8,000
uh 8,000 that also you can follow not a
problem because in MSP we don't follow
this but in prim used to follow this
okay MSP you cannot give unique activity
ID number by default it will give just 1
2 3 4 5 the just numerical numbers it
will have okay so here I have ordered
activities that is fine but for drawing
submission how many days we are taking
okay uh if in my contract if it is
mentioned as 7 days so
I will change 7 days then
okay see I have changed 7 days here so I
need all all uh drawings to be submitted
in 7 days so what I will do I will
select all
and right click there is a option fill
down so if I select that I have 7 days
for all activity.
Okay. Uh for uh for the approval process
let's give 3 days. Okay. So this is what
this details you will collect from your
engineering register or tracker. Okay.
So I have given three. Now select all
right click fill down. So all become 3
days. Okay. This is how you have to uh
feed your
uh this is a shortcut to feed your
duration. If it is a similar duration,
you can just right click and do the fill
down after selecting everything. Okay,
so this is how uh your activity
numbering works and uh uh description
it's not that big deal and the duration.
Okay. Now
there are uh three type of activities we
Please note note down this three.
99%age of the time, okay, we use task
dependent activity. Remaining 1% we use
this start milestone, finish milestone
just for reference. Okay, it is always a
task dependent activity or
it's it can be a milestone activity,
start milestone or finish milestone.
Okay. But if you see here, I'm selecting
one activity here. Contract sign up.
Okay. Uh if you come to details page,
this details is here. Okay. Uh it may be
something like that. But you have to
select this first one. If you keep your
cursor, it will tell details. Okay. If
you select that one or by default, you
will have details here. Okay. Here if
you see there there are activity types.
So these are all activity types. There
are more than that three uh but most of
the time we will use task step and
finish milestone and start milestone.
Others I will just explain but uh you
will not use it uh most of the time. Okay.
Okay. What is task dependent? First let
me explain task dependent. the all
activities which is having any effort uh
like any physical work or any
documentation or any this
pre-construction activity this all will
become as uh task dependent okay it is a
task we have to complete okay so what is
the milestone activity start milestone
and finish milestone this is like uh
these activities are like indicators
okay uh see I will give you an example
here we have an activity contract sign
off. There is no task involved in
contract sign off. We are not going to
do anything. It it it will be signed
somewhere else. We will just receive the documents.
So I can consider this as a
start milestone because it's just
started. It's just starting uh there is
no finish. It's not like we will uh
after signing the contract we always
daily sign something. Nothing like that.
Okay. So we can consider it as a start
milestone. When you are given a start
milestone or finish milestone, you will
see a diamond symbol here instead of
bars because bars means it is having
duration. We have to do something. This
is one day duration, 7 day duration, we
have to do do something. But when it
comes to this uh milestone this diamond,
automatically your activity will become
zero days because it is an indicator
right. uh let's say you are an MEP
contractor okay you are receiving
clearance from for work site clearance
or site posession from civil team uh
that is another contractor okay so you
are having one activity site posession
from civil contractor okay
do you need to do anything in that
activity no it is a milestone it is a
start milestone right so on that time
also you have to give start milestone Okay,
Okay,
finish milestone is something you are finishing.
finishing.
So you want to indicate that let's say
zone one. Okay, last activity I will
give completion of zone one. I can give
one activity completion of zone one. So
completion of zone one other activities
are progressing then maybe civil,
mechanical, electrical works that will
be ongoing. Okay. But this is just
indicator. I will link all activities to
just this one indicator. But this is a
finished milestone activity. Okay. So on
that cases when after handing over also
project closer that is a finish
milestone. Okay. Project start that is a
start milestone. So only for this area
it it it will not be more than five
activities for mean in some cases maybe
Okay. this milestone activities I'm
talking rest all you will have task
dependent by default you will give task
dependent for all activities okay so
this three we will use and there is some
other also level of effort
level of effort is uh you will have one
activity but you will not work in that
activity it can be done by some others
let's say um uh same example MEP you are
MEP contractor okay you are doing a fire
pipe for installation on the roof. Fire
sprinkler works we have to do right. So
you are doing fire sprinkler works.
Okay. After that you can do the
sprinkler piping works but you cannot
install the sprinkler. Okay. To install
the sprinkler fall ceiling should be
completed. Okay. In ceiling maybe you
would have seen in the malls or
hospitals or any buildings or commercial
buildings you can see that uh if you see
sprinkler it is closed. You cannot see
the pipe. You can just see the
sprinklers. It will be hanging outside.
Okay. So, fall ceiling is not part of
that uh fire fire pipe contractor scope.
Okay. So, they will do the piping first.
Then civil team they will do the fall
sealing then again uh this fire team
fire piping team will come and they will
just install the sprinklers. So they
have a dependency with the civil team
because they are the one doing that uh
activity in between. Okay. So I I am
that firepipe contractor. How I will
monitor this project? I will I will have
this uh fire piping on the roof. Okay.
In ceiling. After that there is a fall
ceiling which is not my activity and I
have my sprinkler installation. Where
will I link my sprinkler installation?
to the fire pipe that will give an uh
bad monitoring. Okay. After right after
installing fire pipe, I cannot install
sprinkler. I cannot have activity like
that. In between there is an activity is
there. Okay. So, what I will do? I will
add one activity fall ceiling. Okay. So,
but that activity I will make it as a
level of effort.
So, it is a kind of dummy activities.
Okay. So dummy activities are this level
of effort activities. Uh but uh if you
are mentioned with the contract we have
to use this this this activities as a
level of effort you can use this uh
future otherwise uh don't use it. Okay,
just to keep milestones and uh task
dependent. Okay. Now, um
WB summary you already know uh this is
what this drawing summation is WB
summary. So if you click on activity and
you if you want to make it as a summary,
you can just make it using that one.
Resource dependent is uh
if there is an activity all activities
are resource dependent for us. But if
you just want to highlight this activity
is completely resource dependent, you
can use this one. This also it's not
usable. Okay. Uh so the point here is
you will use finish milestone, start
milestone, task dependent. Okay. So here
I have changed it to task milestone.
Kickoff meeting uh it is a I it's not a
start milestone. I cannot tell task
milestone. It can be one day one day
task. So let it be with the task
department others are task dependent.
Nothing I can change it to milestone. So
so that is what activity type is. And uh
the other other things also let's see
duration type. Okay. Duration type.
This is 100%age of the time we have to
use fixed duration and units. By default
it is also fixed duration and units.
Okay, if you just have fixed units or
fixed units per time or fixed duration
units per time, it will not give a
proper duration and all. It will it will
change to decimals sometimes. And also
why we need to use fixed duration and
units is see
if I'm giving units. Okay. In in in a
EPC project, I will load a resource in
construction part. All the labels,
carpenter, welder, fitter, ste uh all
this all these resources I will use in
construction part. Will I use that same
resource in procurement part? No, I will
not use it. Maybe in commissioning I
will use. Okay. In drawings, can I use
that same resources? No, I cannot use. I
can use only uh indirect labors, not
direct labors. Okay, there is a
difference difference difference between
indirect labors and direct labors.
Direct labor means the persons who is
doing the physical work at site. Okay,
indirect labors are the supervisor,
foreman, surveyor, engineer, manager.
These are all indirect labors. So here I
have work for indirect labors, not
direct labors. And here I I again it's a
mixed it's indirect labor for two
activity, direct labors for sorry direct
labor for two activity, indirect labors
for some others.
So I have different different units and also
also
I I I will measure this activities by
numbers civil layout maybe if two
layouts are there one layout completed
50%age I will feed as completed two
layouts completed 100 100%age I will
feed right and procurement if it is a PO
issued completed PO not issued not
completed 100% are zero okay in
construction it depends on the activity
earth work it's in cubic meter when I'm
excavating it's in cubic meter tunneling
uh it may be in meters okay services
also numbers are meter something so if
you see each activities they're having
unique uh unique unit so I should if I'm
measuring all the project at once okay
I'm having overall project summary
percentage see I want to see north side
utility tunnel how much percentage it
completed so if I'm having each units
are different different I cannot have a accurate
accurate
percentage completion summary
percentage. So that is why what is the
common thing for all the activities if
you see that is duration
right all the activities are having
duration duration is common for all
activities it will not change but units
will change here are different units
here different units right so that is
why you always should have fixed
duration and units in an EPC project
okay um others you will not use use it
but uh fixed units If you are having
common units for all the resources, all
the activities, you can use fixed units,
but that is also not recommended.
Duration is the right thing to do. Okay.
Percentage completion also the same
thing what I said. Okay. Duration is the
common unit. We can measure the
percentage complete uh properly. If I'm
having physical percentage completion, I
have physical works in construction
part. I don't have physical loads in
engineering part or uh procurement part.
So it will not give right and units also
like I mentioned units are having
different different thing here it is a
numbers one activity it can be meters
one activity it is square meters one
activity it can be cubic m so that will
also not work. So percentage complete
type better keep it to duration. Okay.
Okay.
So these are all the things only the uh
just for explanation. Okay. Otherwise
you can uh just follow what whatever is
default here you can just follow that
only thing you have to do is this uh if
it is a milestone you will just make it
as a milestone only that thing you have
to do here. Okay. And calendar [clears throat]
[clears throat]
by default my calendar is coming here.
Okay. But if you created project then if
you created the calendar what will happen?
happen?
uh sometimes we will we will create the
project first and uh we will forget to
create the calendar first. So we will
make a project then we will create
calendar on that cases
uh you you have to manually feed your
calendar. Okay, that how to do that I
will show you. So see by default I'm
having activity ID, activity name,
original duration, start and finish.
Okay, this is customizable. Everything
is customizable here. Okay. So let's
right click here we see columns or here
you can see the columns icon. You can
click on any of that. If I click columns
you will be opened with two options.
Okay. This is selected options. This is
what you are seeing here. Activity ID,
activity name, original duration, start
finish. Okay. These are all your
options. Most of the things are hidden.
So now I have to I I have to insert the
calendar column so that I can see
activity by activity where are all
calendar order added where are all
calendar not ordered. Okay. So I have to
identify where is calendar because see
it's a long list you have to search
where it is. Okay. Uh so better what I
will do is give a control F it will be
opened with this tab. So search calendar.
calendar.
See I'm having calendar here. Now what I
have to do from available options I have
to move to selected options. So I click
this. See this options I if I click from
here it will move here. So calendar is
here. So if I click apply calendar will
come here. I don't want this calendar
after activity ID. I want this is after
finish. So what I will do? I'm selecting
calendar. I'm just moving it to the
bottom after finish. So click apply. Now
I'm having calendar here. Now click
okay. See all activity
calendars cmda.
I guess that Chennai Metro development
authority something I have created
right. So that cmd calendar already
added because you remember we have
selected default CMDA. So wherever new
project created this CMDA will be
default calendar for that project. Okay.
But if you want to change it, okay, you
created with some other calendar, you
want to change it. So what you have to
do, double click here. Okay, you will
have options.
Select ABC calendar. So this activity
having ABC calendar, others having CMDA.
Again the same like a duration, select
all, right click, do the fill down, all
activities will be changed to ABC
calendar. So this is how you have to
change the calendar. Okay.
If you already created calendar right
before the project installation, no need
to worry about this thing. Otherwise,
you have to change it manually like I did.
So, this is all about activity creations.
creations.
Uh, anybody having any doubt here so
Sorry
anyone answer this with anyone.
Okay. Okay.
Okay. Refiner PC CM contract milestone
I'm just using control E for the filter
down shortcut. >> Okay,
>> Okay, fine. Summary including summary
changed. Okay. Fine. Okay.
for 2 hours
2 hours. So
Okay. So, activity activities.
that next important heart of planning
sequence of activities. Okay.
activity relationships. Okay. Four type
technically it's okay
Okay. Now this is an activity. This is
an activity. This is activity number
one. Activity number two. Okay. Here
this is activity start. This is activity
finish. Okay. This is activity start.
This is activity finish. Activity is
started uh starting here and it is
getting finished here. Okay. Now first
uh what we are seeing is finish to start.
start.
Okay this relationship because this is
what 90%age of the time you are going to
use. Okay. So this activity to activity
is linked like this. Okay. After
finishing this activity this activity
will start. So that relationship is
called finish to start. Okay. You have
to finish this activity to start this
activity. You cannot start this activity
without finishing this activity.
Example, okay, this is a uh material
delivery, pipe delivery example. This is
a pipe delivery. Okay, this is pipe
installation. Okay, this activity should
be completed. Pipe should be delivered.
Then only you can start your pipe
installation. Right? So your pipe
delivery is finished. Then you are
starting your pipe installation. Meaning
pipe deliver you you delivered your
pipes into site with that pipeline you
are starting with that pipes you are
starting your pipe activ pipe
installation activities okay or drawing
drawing approval physical installation
you need drawing to install the uh work
physically. So there also you will use
finish to start. So material delivery to
site installation or drawing approves to
site installation this all will comes
under finish to start relationships that
is why I'm telling 90% of the time you
will use this okay this is one relationship
relationship
okay this is easiest one finish to start then
then
next relationship is you you can take a
screenshot or something
just confirm then I will go for the next one.
start to start
to start. This is one activity and this
is another activity. So here this is the
start. This is the finish. Here this is
the start. This is the finish. Okay.
So both activity will start at the same
time. Okay. But it can be finished in
different time. This is 5 days. This is
7 days. So but you will start the both
activity at the same time. So that you
will give start to start relationship.
Example maybe this is floor one
activity. This is floor two activity.
You are starting both floors at the same
time with separate separate resources.
At that time you can link this
activities as a start to start. Okay.
But you will not use this most of the
time in this manner. You will use it in
different manner like
this is another two activities. Okay.
And this is your start. This is your
finish. This is your start. This is your
finish. This also start to start. Okay.
But the difference between the start is
let's say 2 days which means SS plus 2
days. Start to start plus 2 days. This
two days is lag. Okay. So with the lag
you can use the start to start example
this is a excavation okay excavation for
pipelines this is installation pipe
installation for pipeline okay here you
don't uh let's say this is 100 m
excavation this is 100 m pipling okay
here you don't need to wait for entire
100 m to complete let's say uh after 2
days uh 30 m of excavation complete
completed. So you'll start installing
that pipeline in that 20 m next day. But
your excavation also will be continuing.
Pipe installation also will be
continuing parallelly. Wherever you
excavated, you will start installing the
pipe installation with some lag. So
there you will use SS plus two. Okay,
this is how this uh SS relationship
Just take screenshot.
again are not down. So I will move to
Next to finish to finish this also same. Okay. Uh if two
this also same. Okay. Uh if two activities are working like this. Okay.
activities are working like this. Okay. Start and finish. Start and finish. It
Start and finish. Start and finish. It is starting with different time,
is starting with different time, different dates but finishing at the
different dates but finishing at the same time. That is finish to finish.
same time. That is finish to finish. Here also you can use lag f of plus two
Here also you can use lag f of plus two or something. Okay. Same way uh the same
or something. Okay. Same way uh the same example I told you you can link as a
example I told you you can link as a finish to finish
to finish but finish to finish with the lag
lag 2 days. This difference is 2 days.
2 days. This difference is 2 days. So this is example for finish to finish.
So this is example for finish to finish. Okay. Wherever you you are using start
Okay. Wherever you you are using start to start at that uh for that activities
to start at that uh for that activities you can use finish to finish also. More
you can use finish to finish also. More or less it works in the same way. Okay.
or less it works in the same way. Okay. Take this uh screenshot or something. We
Take this uh screenshot or something. We will move to this.
Start to finish. Okay. This is one activity. This is one
Okay. This is one activity. This is one activity. Okay.
activity. Okay. That is a start. It is a finish. This is
That is a start. It is a finish. This is a start. This is a finish. Okay. Uh here
a start. This is a finish. Okay. Uh here you cannot start this activity uh you
you cannot start this activity uh you cannot finish this activity without
cannot finish this activity without starting this activity. There's a slight
starting this activity. There's a slight difference between finish to start and
difference between finish to start and start to finish. Okay. Finish to start
start to finish. Okay. Finish to start you have to finish this then only you
you have to finish this then only you can start this activity. But for the
can start this activity. But for the start to finish to start uh after
start to finish to start uh after starting this activity you can finish
starting this activity you can finish this activity. Okay. That is why we are
this activity. Okay. That is why we are not having this in construction this
not having this in construction this relationship. Okay. If I'm giving you an
relationship. Okay. If I'm giving you an example
example two security guards are working. One is
two security guards are working. One is doing day shift, one is doing night
doing day shift, one is doing night shift. Okay. Night shift uh security
shift. Okay. Night shift uh security guard should take responsibility. Should
guard should take responsibility. Should start his duty. Then only the day shift
start his duty. Then only the day shift guy can finish his own. It's not like he
guy can finish his own. It's not like he can finish after 1 hour gap he can
can finish after 1 hour gap he can start. It it cannot be like that. Right?
start. It it cannot be like that. Right? Security should be there.
Security should be there. Right? So he need to take over his duty
Right? So he need to take over his duty then this guy will get released from his
then this guy will get released from his duty. So that is an example for start to
duty. So that is an example for start to finish. Okay. But this we will not use
finish. Okay. But this we will not use it just for if you are if you have been
it just for if you are if you have been asked in interview whe start to finish
asked in interview whe start to finish activity you can uh confidently tell I
activity you can uh confidently tell I never used this relationship. Okay. In
never used this relationship. Okay. In our contract it is mentioned we should
our contract it is mentioned we should not use this one. But if they're asking
not use this one. But if they're asking for example you can give this same
for example you can give this same example. This is a critical word
example. This is a critical word example. Okay.
So let's close this. So this one we will uh detail see uh in
So this one we will uh detail see uh in the next class how to apply in our uh
the next class how to apply in our uh activity list. Okay.
If you want again also next class I will explain then we will move on. Okay. Now
explain then we will move on. Okay. Now I'm not closing this one because it is
I'm not closing this one because it is after applying to the activities we will
after applying to the activities we will see this one. Okay.
see this one. Okay. Right. Okay. That's it for
Right. Okay. That's it for let's uh connect again Monday then we
let's uh connect again Monday then we will continue. Okay.
>> Okay sir. >> Okay. Thank you. Thank you.
>> Okay. Thank you. Thank you. Bye.
Bye. Bye.
Click on any text or timestamp to jump to that moment in the video
Share:
Most transcripts ready in under 5 seconds
One-Click Copy125+ LanguagesSearch ContentJump to Timestamps
Paste YouTube URL
Enter any YouTube video link to get the full transcript
Transcript Extraction Form
Most transcripts ready in under 5 seconds
Get Our Chrome Extension
Get transcripts instantly without leaving YouTube. Install our Chrome extension for one-click access to any video's transcript directly on the watch page.